TEG Dehydration & Fuel Gas Treatment Package
TEG Dehydration & Fuel Gas Treatment Package
Project: Recent modular project for Iraq
Package: TEG Dehydration & Fuel Gas Treatment Package
Capacity: 155 MMSCFD
The process Module for TEG Dehydration & Fuel Gas Treatment Package are fabricated in UAE and transported from Jebel Ali Port by ship to Iraq on Date: June to September 2023.
Design, Engineering and procurement have been performed in Thailand.
Fabrication has been performed in UAE.
This is a successful project completed in approximately 20 months
Scope of Work:
Scope of work is to design, procurement, fabrication, factory test and site commission the complete package
Includes process / performance guarantees
The Module is included for 9 skids, pipe racks and 3 standalone columns.
- GAS VALVE SKID (156-SK01A/B)
- GAS/LEAN TEG HEAT EXCHANGER SKID (156-SK02)
- FLASH VESSEL SKID (156-SK03)
- TEG RECIRCULATION PUMPS SKID A/B (156-SK04 A/B)
- REBOILER SKID (156-SK05)
- PIPE RACK (156-SK06)
- DUST FILTER SKID (510-SK07)
- CHEMICAL INJECTION SKID ANTIFOAM (156-SK08A)
- DRY GAS SEPARATOR SKID (156-SK09)
- TEG ABSORBER (SA01)
- TEG PREPARATION DRUM (SA03)
- DESULFURIZATION ABSORPTION TOWER (156-SA05)
12 December 2023
Viewed 746 time